Progress to Date
A masterplan for Ashford was published in the Greater
Ashford Development Framework (GADF) 2005. Today the masterplan
is being implemented and the key projects are rapidly changing the
face of Ashford.
Residential and Commercial
- Stour Centre remodelling.
Opened September 2007.
- County Square
retail extension. Opened spring 2008.
- Planning permission granted for 3000 dwellings on three large
sites (Park Farm south and east, Cheesemans Green and the former
Templer Barracks sites).
- Completion of the first 50,000ft of proposed 1.25 million ft
space at Eureka Park.
Education and Health
- A new Primary Care Health Centre opened in 2006 in south
Ashford.
- Planning permission submitted by South Kent College for
a multi-million further education facility Ashford Learning
Campus.
- Opening of John Wesley Primary School in Singleton in September
2007.
- Plans to create a further 15 primary schools and three
secondary schools over the next 20 years.
Environment
- Mid Kent Water is investing
£24.4 million into improving water supply to the Mid Kent area
including a new water main between Bewl Water and Ashford.
- Southern Water is investing
over £40 million into infrastructure necessary to accommodate the
planned growth in Ashford.
- The Singleton Environment
Centre community facility opened in May 2008.
Transport
- Junction
10, M20. Work on a £7 million scheme to tackle congestion and
improve capacity was completed in September 2007.
- Ring Road. Work to transform the former ring road around the
town centre into a series of two-way streets, which will open up
the town centre and make it a more plesant environment was
completed in October 2008.
- Newtown Bridge. Works to improve access to the south of the
town centre via Newtown Road Bridge was completed in December
2008.
- A new traffic signal controlled junction at Romney Marsh
Road/Victoria Road junction was completed in October
2008.
- Planning approval has been given for a new road called
Victoria Way linking
the town centre and station with south Ashford. Work will
start in spring 2010.
- Work on improving the capacity of Junction
9 of the M20 and nearby Drovers Roundabout including building a
new foot/cycle bridge over the M20 will start in spring 2010.
- A new fast and high frequency bus service SmartLink is due to launch in
2012, following the introduction of a Park and Ride
scheme.
- M20 J10a consultation complete by September 2008. Scheme on
track for delivery by 2013 (subsequent to approval).
Telecommunications
- Broadband. Wireless broadband available in Ashford from
February 2006. Telecommunications and Broadband Strategy completed
and project to develop fibre optic provision in Ashford
underway.